Finnish energy generation equipment company Wärtsilä has announced that it is proceeding with the construction of a 200MW flexible baseload power plant in Colombia, despite the challenges brought by COVID-19.

The €100 million ($118.9 million) project is being built in the Colombian province of Córdoba.

Wärtsilä won the engineering, procurement and construction contract for the project from Termotesorito in June 2020.

Termotesorito is a joint-venture enterprise between private utility companies Celsia and Proelectrica, and the natural gas provider Canacol.

Subscribe to PE’s free, weekly newsletter to read more stories like this

See our coverage of on-site power and cogeneration projects

Wärtsilä is installing some eleven 50SG engines which will be fueled by natural gas from nearby gas wells.

When operational, the flexibility of the fast-starting power plant will provide critical grid balancing capability as Colombia incorporates increasing levels of intermittent energy from renewable sources, such as solar and wind. It will also provide back-up power for the system in case of shortage.

Engineering of the power plant is completed. All engines and generators have been tested at the factory and are ready for delivery, and auxiliary equipment is being manufactured. The construction project is scheduled to commence in April 2021.

àlvaro Acevedo, technical director for El Tesorito, said: “We have a long-term capacity contract to deliver a reliable supply to the grid, and to supply efficient energy when needed. For these reasons, we required a proven solution from an experienced provider with a strong track record. The flexibility, reliability and efficiency of the Wärtsilä plant, which can be started and stopped in a matter of minutes and which has a very low water consumption, is exactly what is needed as we integrate more and more renewables into the system.”

— — — — —

POWERGEN International will be Jan. 26-28 in Dallas, and the call for speakers and presentations is now open until May 17. If you want to highlight an on-site power projects–from CHP to microgrids and more–you can submit a session idea for the New Energy Mix, the Future of Electricity and Trends in Conventional Power tracks.