Southern California Edison (SCE) has awarded PAR Electrical Contractors Inc. (PAR), a subsidiary of Quanta Services,  a contract to complete the construction of Tehachapi Renewable Transmission Project (TRTP) segment seven and portions of segment eight.

 The contract states that PAR will install double circuit 500-kV overhead transmission lines, environmental mitigation and compliance, foundation installation, tower erection and conductor installation.

Quanta expects segment seven to be completed by the end of 2014. Portions of segment eight will be completed by February 2015.