Boilers, Gas, Retrofits & Upgrades, Retrofits & Upgrades

Gas-fired power plant restoration contract awarded to Wood Group

Wood Group GTS on August 28 said it has secured a contract with Pasadena Water & Power (PWP) for the repair and restoration of the GT-1 generating unit at the Glenarm Power Plant in Pasadena, Calif. The scope of work involves refurbishment of a Pratt & Whitney FT-4 gas turbine generator, including overhaul of the gas generator, supply of a refurbished power turbine and related ancillaries, and turnkey installation of all equipment.

The scope of work may extend to include upgrade of the gas turbine control system and other related equipment as necessary.

The work is scheduled to commence in August 2012 and is estimated to take about seven months to complete.

Read more gas retrofits and upgrades news