Coal, Hydroelectric, Renewables

Alstom signs EUR500m equipment contract for Brazil’s Belo Monte hydro project

Alstom has signed a contract worth approximately EUR500m ($684m) with Norte Energia of Brazil to provide power equipment for the Belo Monte Dam, the world’s third-largest hydroelectric power plant with a planned capacity of 11.23 GW.
 
The Belo Monte project will dam the Xingu river in Brazil’s northern Pará state.
 
Alstom will lead a consortium that includes German Voith and Austrian Andritz for fourteen 611 MW Francis turbine-generator sets and the six smaller Bulb units. Alstom will supply seven Francis units, hydro-mechanical equipment and associated gas insulated substations (GIS) for the fourteen large-scale units.

It is expected that Belo Monte will take eight years to be built. When operating at full capacity, Belo Monte will meet the electricity needs of 35m people.

For more hydropower news, click here