Home>Topics>Reactor Building
  1. All
  2. Article
  3. Print
  4. Web
  5. Text

Reactor Building

Reactor Building news and technical articles from Power Engineering. Search Reactor Building latest and archived news and articles

  1. China: Taishan 1 EPR dome Installed Successfully by Areva

    Web

    Wed, 9 Nov 2011

    The dome installation on the reactor building of unit 1 of the EPR nuclear ..... first concrete pouring of the reactor building raft.This success constitutes ..... carry out the civil work on the reactor building .The vast operation to maneuver

  2. Nuclear power plant receives major component

    Article

    Tue, 21 Feb 2012

    shipped on-time to China. After some storing time on site, the next step will consist of introducing the RPV in the reactor building of Unit 1 before completing its installation in the reactor pit. The RPV introduction will be the next major milestone

  1. Construction of Finland's Olkiluoto 3 reaches new milestone

    Article

    Tue, 22 Jun 2010

    installation of the reactor pressure vessel in the reactor building . The reactor pressure vessel was first transported ..... the reactor containment, and then lifted into the reactor building before its final vertical introduction into the

  2. UK nuclear power programme falls behind schedule

    Article

    Fri, 27 Aug 2010

    27 August 2010 - The schedule for the UK's nuclear reactor building programme has slipped behind already, the safety regulator has admitted, reinforcing concerns that the first reactor will not

  3. Leak detected at nuclear power plant in Canada

    Article

    Wed, 2 May 2012

    April 26, Hydro-Québec informed the Canadian Nuclear Safety Commission (CNSC) of a heavy water leak in the reactor building at the 675 MW Gentilly 2 nuclear power plant near Bécancour, Quebec, the commission said on May 2. The CNSC said

  4. Koodankulam's Reserve Water Requirements

    Web

    Sun, 6 May 2012

    reservoir is planned to be located at an elevation of 35 metre which is much above the safe grade elevation of the reactor building " (NEERI 2003). While giving its nod to the project, the Atomic Energy Regulatory Board (AERB) made the following

  5. Timeline of events in Japan

    Article

    Wed, 28 Sep 2011

    sieverts per hour inside the Unit 1 reactor building . The high readings will keep ..... workers entered the damaged reactor building of Unit 1 at the Fukushima Daiichi ..... radiation levels inside the reactor building . If the ventilator works as

  6. Japan's Nuclear Crisis: Timeline of Events

    Print

    Wed, 1 Jun 2011

    workers entered the damaged reactor building of Unit 1 at the Fukushima Daiichi ..... radiation levels inside the reactor building . If the ventilator works as ..... set up air coolers outside the reactor building to cool the water in the containment

  7. Timeline of events in Japan

    Print

    Sun, 1 May 2011

    12 blew the roof off another reactor building . TEPCO begins injecting sea ..... radioactive water has leaked from a reactor building . WEDNESDAY, MARCH 30 TEPCO ..... set up air coolers outside the reactor building to cool the water in the containment

  8. Decommissioning of Fukushima nuclear plant to take 30-40 years

    Article

    Wed, 21 Dec 2011

    lessons learned from work on units 3 and 4, while for Unit 2, TEPCO will develop a plan once the inside of the reactor building has been decontaminated and the condition of existing used fuel handling equipment has been assessed. Subscribe