Power Engineering

Computer Simulation Reduces Time And Cost Of Wet Scrubber Design

By Douglas J. Smith, IEng Senior Editor

USING COMPUTER simulation to evaluate the performance of wet scrubbers has saved Babcock & Wilcox (B&W) up to $70,000 and four weeks of work. Because the design of wet scrubbers depends upon the fuel being burned and the amount of sulfur in the fuel, B&W must custom design each scrubber they sell. When designing a scrubber the engineer has to balance a number of competing factors including its geometry, gas flow velocity, sulfur dioxide removal rate, slurry droplet carry-over rate and the pressure drop.

In the past design engineers constructed a 1/8-scale model of the scrubber, which was then used to evaluate the performance of the design. The model, made from Plexiglas, made it possible to observe the movement of the gas and liquids within the absorber cylinder. A major drawback of using models is they cost $50,000 to $80,000 each. In addition to the cost is the length of time to construct the model and/or modify the model.


Wet Scrubber Absorber Module
Click here to enlarge image

To reduce engineering costs B&W decided to augment the physical model testing of wet scrubbers with computational fluid dynamics (CFD) analysis software to simulate scrubber performance. The CFD software, CFX purchased from AEA Technology, Pittsburgh, Pennsylvania, is capable of two-phase modeling. This was very important to B&W because their wet scrubbers must deal with gas and liquids.

The first step in the process was the construction of a large-scale physical model that B&W used to develop the following quantitative data:

  • Pressure drop through the scrubber
  • Tray characteristics
  • Liquid fractions within the absorber
  • Mist eliminator pressure drop
  • Droplet loading to the mist eliminators
  • Amount of carryover and gas
  • Liquid flow patterns

The model was tested with a wide range of gas velocities, slurry fluxes and spray header arrangements. This phase of the project took B&W four years to collect and analyze all of the data.

Simulated modeling

Using computer simulation, B&W engineers have designed a wet scrubber for which the base design was established in the large physical model. The first step, before they could use the simulation program, was to update the existing digital scrubber model to show the scrubber inlet, absorber trays, the spray zones and the mist eliminators. In operation, the computer simulates the flue gas as it enters uniformly through the side inlet and exits through the top of the scrubber. It also simulates the water entering the spray headers and exiting, at uniform pressure, at the bottom of the scrubber.

Modifying the model to match the new design parameters took approximately one week. Another week was spent running the CFX simulations to gauge the performance of the system. Using the scrubber simulation allowed the gas and water flow patterns to be observed under six different operating conditions. With the simulator the engineers are able to modify the scrubber's configuration and optimize its design very quickly. One person at a cost of less than $15,000 did the initial modeling, simulation and analysis. Previously three people were required when using the Plexiglas model.

"Being able to evaluate many different configurations has improved the quality of our designs," says Paul Williams, senior advisor at B&W. According to Williams, the computer simulation gives B&W the ability to evaluate multiple design options quickly and at lower costs.

Sponsored by FLSmidth

Related Articles

B&W Vølund to build waste-to-energy power plant in Scotland

In a consortium with Interserve, Babcock & Wilcox Co.’s (B&W, NYSE:BWC) subsidiary, Babcock & Wilcox Vølund A/S (B&W Vølund), will engineer, procure and construct (EPC) a waste-to-energy (WTE) power plant for Viridor UK. The contract is worth approximately $230 million.

B&W Canada to provide nuclear services for Bruce Power units

The Babcock & Wilcox Company (B&W, NYSE:BWC) announced that its subsidiary Babcock & Wilcox Canada Ltd. (B&W Canada) has entered into a long-term service agreement with Bruce Power, valued at nearly $300 million.

Follow Power Engineering on Twitter
Latest News

PNM files ownership plan, coal supply deal with regulators

New Mexico's largest electric provider says it's on track to meeting a deadline for submittin...

Oklahoma attorney general challenges EPA's clean-air plan

A plan by the U.S. Environmental Protection Agency to reduce emissions from coal-fired power ...

Wave Energy Week will mix marine energy developers with traditional hydropower

Oregon Gov. Kate Brown, Democrat, has proclaimed “July 13-17, 2015 to be Oregon Wave Week in ...

Public Service Company of Oklahoma seeks rate increase

Public Service Company of Oklahoma is asking for a 13.6 percent rate increase it says is need...

GAO looks at reliability impacts of changing power generation mix

The Government Accountability Office (GAO) on June 29 released a study provided a month befor...

On the day after MATS decision, Bernstein sees only a limited reprieve for coal units

In light of the U.S. Supreme Court ruling against the EPA's Mercury and Air Toxics Standards ...

Pence says Indiana will not comply with coal plant regulations

Indiana will not comply with President Barack Obama's plan to battle climate change by requir...

Westermost Rough offshore wind park enters operations

The 210-MW offshore wind power plant, Westermost Rough, has entered operations. The project w...

Power Engineering Current Issue

03/01/2014
Volume 118, Issue 3
1403PE-cover
Products Showcase
Dynamic Fluoride Ion cleaning DFIC of industrial natural gas turbines Hi-Tech Furnace Systems

Dynamic Fluoride Ion Cleaning of IGT Parts

The Dynamic Fluoride Ion Cleaning (DFIC) Process from Hi-Tech Furnace Systems is able to clean deep, narrow cracks of oxides by cycling between negative, atmospheric, and positive pressure.

Archived Articles

2000 | 2001 | 2002 | 2003 | 2004 | 2005 | 2006 | 2007 | 2008 | 2009 | 2010 | 2011 | 2012 | 2013

Power Industry Wire News

NW Natural Announces Dividend and Schedules Conference Call to Review Results for the Three and Six Months Ended June 30, 2015

NW Natural Announces Dividend and Schedules Conference Call to Review Results for the T...

Vantage Drilling Responds to News Reports Regarding Petrobras

Vantage Drilling Responds to News Reports Regarding Petrobras

National Grid Drives Innovation Through REV Demonstration Projects

National Grid Drives Innovation Through REV Demonstration Projects

Cardinal Resources' $28.8 Million Cameroon Red Bird Contract Advances; Company Expects Financing Completed, Implementation, in Q3-15

Cardinal Resources' $28.8 Million Cameroon Red Bird Contract Advances; Company Expects ...

Letter From CGE Energy (McKenzie Bay Intl.) President Bryan Zaplitny

Letter From CGE Energy (McKenzie Bay Intl.) President Bryan Zaplitny

Power Engineering

Article Archives for Power Engineering Magazine

Continuing Education

Professional Development Hours

To access a course listing associated to a specific topic listed below, click on the topic of choice from the list below.

Latest Energy Jobs

View more Job Listings >>