Developers of a planned 850 MW coal-fired plant outside Sandersville, Ga. told the Macon Telegraph they are in a “dead sprint” to begin construction of the facility by April 13, the deadline for the U.S. Environmental Protection Agency to finalize its New Source Performance Standard.

If the $2.1 billion Plant Washington, which is being developed by Allied Energy Services, is under construction by the time the NSPS rule is finalized, it will be exempt from the rule that would limit carbon dioxide emissions to 1,000 pounds per MWh for new power plants. Although the rule’s deadline is April 13, the Washington Post has reported the rule may be rewritten, causing the EPA to delay finalizing the rule.

Although a delay would make it easier for Plant Washington to begin construction before the rule is implemented, it could also cause more regulatory uncertainty that has already led to companies abandoning new coal-fired power projects, according to the Telegraph.

Delays in EPA rules have already led to problems at Plant Washington. According to the report, developers were unable to complete the plant’s boiler design until the Mercury and Air Toxics Standard was finalized last week. Until the boiler design was finalized, the developers could not line up financing and sign engineering, procurement and construction contracts.

A representative from Allied Energy Services told the Telegraph the company expects the contracts will be in place and the project will be far enough along to be exempt from greenhouse gas requirement.

Read more new coal-fired projects news

Sponsored by FLSmidth
Related Articles

Weekly Coal Production Report

The Weekly Coal Production Report has been updated for the week ended March 14, 2015.

San Juan Generating Station coal-fired New Mexico regulators shut down

New Mexico regulators to hear from public about power plant

New Mexico regulators are scheduled to take more public testimony on a plan to shutter half of an aging coal-fired power plant that supplies communities around the Southwest.

Follow Power Engineering on Twitter
Latest News
France energy bill boosts renewables, cuts nuclear

French bill seeks to boost renewable energy, cut nuclear use

France's lower house of parliament has approved a bill aimed at boosting renewable energy and...
Duke Energy W.C. Beckjord coal-fired power plant

Shut down coal-fired power plant to house energy storage system

Duke Energy (NYSE: DUK) is teaming with LG Chem and Greensmith to convert a shut down coal-fi...
Areva's European Pressurized Reactor (EPR)

EDF offers Areva $2bn offer for nuclear reactor unit

EDF has offered Areva a €2 billion ($2.2 billion) approach for Areva’s nuclear reactor busine...
Beaver Valley nuclear power plant in Pennsylvania

Beaver Valley nuclear unit returns to service

Unit 1 at the Beaver Valley nuclear power plant in Pennsylvania returned to service following...
Beacon Power Chugach Electric Association flywheel and battery storage systems

Beacon Power teams on energy storage systems in Alaska

Beacon Power, a manufacturer of flywheel energy storage systems, signed an agreement to suppl...
Entergy's Pilgrim nuclear power plant in Massachusetts

Pilgrim nuclear plant back online after $70M upgrade

The only nuclear power plant in Massachusetts is back on line after a $70 million, monthlong,...
Indian Point Unit 3 nuclear power plant in New York

Indian Point 3 returns to service following transformer fire

Indian Point Unit 3 in New York returned to service more than two weeks after a transformer f...
Susquehanna Unit 2 back online after refueling outage

Susquehanna nuclear Unit 2 completes refueling outage

Unit 2 at PPL’s (NYSE: PPL) Susquehanna nuclear power plant in Pennsylvania has returned to o...
Power Engineering Current Issue
03/01/2015
Volume 119, Issue 3
1503pe-cover
Products Showcase
Dynamic Fluoride Ion cleaning DFIC of industrial natural gas turbines Hi-Tech Furnace Systems

Dynamic Fluoride Ion Cleaning of IGT Parts

The Dynamic Fluoride Ion Cleaning (DFIC) Process from Hi-Tech Furnace Systems is able to clean deep, narrow cracks of oxides by cycling between negative, atmospheric, and positive pressure.

Archived Articles

2000 | 2001 | 2002 | 2003 | 2004 | 2005 | 2006 | 2007 | 2008 | 2009 | 2010 | 2011 | 2012 | 2013 | 2014 | 2015

Power Industry Wire News

MIC President Marybeth Miceli Named to AATA Board of Directors; AATA to Provide Free NDT Job Training to Vets, Disadvantaged Young Adults

MIC President Marybeth Miceli Named to AATA Board of Directors; AATA to Provide Free ND...

Alexium Anticipates Potential Addressable Revenue of More Than US$10M for 2015

Alexium Anticipates Potential Addressable Revenue of More Than US$10M for 2015

Upcoming Greenhouse Webinar Teaches Companies How to Engage Engineers in Hiring Top Tech Talent

Upcoming Greenhouse Webinar Teaches Companies How to Engage Engineers in Hiring Top Tec...

Perma-Fix Environmental Services to Present at the Marcum MicroCap Conference

Perma-Fix Environmental Services to Present at the Marcum MicroCap Conference

Blue Earth Receives Notice From NASDAQ That the Company Is No Longer Subject to a Possible Delisting

Blue Earth Receives Notice From NASDAQ That the Company Is No Longer Subject to a Possi...

Power Engineering

Article Archives for Power Engineering Magazine

Continuing Education

Professional Development Hours

To access a course listing associated to a specific topic listed below, click on the topic of choice from the list below.

Latest Energy Jobs

View more Job Listings >>