A federal appeals court recently ruled that government regulators may attempt to halt construction projects at power plants if they believe the companies did not properly calculate potential increases in air pollution, according to a report from the Associated Press.

The case, United States v. DTE Energy Co., was filed when the U.S. Environmental Protection Agency sued DTE Energy (NYSE: DTE) in 2010. According to the report, DTE Energy was replacing key boiler parts at its Monroe Unit 2 coal-fired power plant without installing pollution controls, which the EPA said were required under the Clean Air Act because the company was performing a major modification of the facility. DTE, however, said the project was only routine maintenance and exempt from the requirement.

DTE performed the calculations required by the EPA and concluded there would be an increase in emissions, but the increase would result from a higher demand for electric power and not the plant modifications. The EPA, however, claimed the project would result in a significant net emissions increase, according to the AP.

Although a federal judge ruled the EPA went to court too soon, the 6th U.S. Circuit Court of Appeals overturned that decision, stating the law does not block the EPA from filing suit on suspected violations of its regulations. The court did not rule on whether DTE was in compliance with regulations, however, and returned the case to the district court.

The ruling does not allow the EPA the ability to question projections on a power plant, however, but does allow the agency to bring an enforcement action at any time to ensure the projections were “made pursuant to the requirements of the regulations.”

Read more business regulation news

Sponsored by FLSmidth

Related Articles

 EU investigates GE, Alstom $17B acquisition

EU investigates GE, Alstom $17B acquisition

The European Commission is conducting an in-depth investigation on whether GE's (NYSE: GE) proposed acquisition of Alstom SA’s Thermal Power, Renewable Power & Grid businesses will cause large gas turbines costs to rise.

 Virginia regulators schedule hearing on solar project

Virginia regulators schedule hearing on solar project

Virginia regulators have scheduled a public hearing for Dominion Virginia Power's proposed utility-scale solar power project in Fauquier County.

Follow Power Engineering on Twitter

Latest News

[Image Gallery]

 Enbridge’s Texas wind project reaches commercial operation

Enbridge’s Texas wind project reaches commercial operation

Enbridge’s 110-MW Keechi Wind Project has reached commercial operations in Jack County, Texas.
 Entergy names new board of directors

Entergy names new board of directors

Entergy Corp. (NYSE: ETR) has elected Patrick J. Condon and Karen A. Puckett to the company’s...
 Iran & Russia to produce nuclear fuel

Iran & Russia to produce nuclear fuel

Iran and Russia signed a deal to jointly produce nuclear fuel in Iran.

 Nuclear power deal between Hungary, Russia to be secret for 30 years

Nuclear power deal between Hungary, Russia to be secret for 30 years

Details of a nuclear power expansion deal between Hungary and Russia will be kept under wraps...
 Kansas' largest electric company seeking $152M rate increase

Kansas' largest electric company seeking $152M rate increase

The largest supplier of electricity in Kansas is asking state regulators to increase its rate...
 Energy company says it has secured funding for wind farm

Energy company says it has secured funding for wind farm

The energy company planning an offshore wind farm near Block Island says it has secured more ...
 Duke Energy says it will drop nuclear fee off Florida bills

Duke Energy says it will drop nuclear fee off Florida bills

One of Florida's largest power companies says it will go ahead and drop a nuclear power fee n...

Power Engineering Current Issue

02/01/2015
Volume 119, Issue 2
1502PE-cover

Products Showcase

Dynamic Fluoride Ion cleaning DFIC of industrial natural gas turbines Hi-Tech Furnace Systems

Dynamic Fluoride Ion Cleaning of IGT Parts

The Dynamic Fluoride Ion Cleaning (DFIC) Process from Hi-Tech Furnace Systems is able to clean deep, narrow cracks of oxides by cycling between negative, atmospheric, and positive pressure.

Archived Articles

2000 | 2001 | 2002 | 2003 | 2004 | 2005 | 2006 | 2007 | 2008 | 2009 | 2010 | 2011 | 2012 | 2013 | 2014 | 2015

Power Industry Wire News

BioCNG, LLC Announces Expansion of St. Landry Parish Solid Waste District BioCNG(TM) System to Include Mother-Daughter Fuel Station

BioCNG, LLC Announces Expansion of St. Landry Parish Solid Waste District BioCNG(TM) Sy...

Letter From CGE Energy President Bryan Zaplitny

Letter From CGE Energy President Bryan Zaplitny

UGE International and OTEPI Renewables Selected to Supply Solar Energy Systems for Retail Chain's Portfolio of Facilities

UGE International and OTEPI Renewables Selected to Supply Solar Energy Systems for Reta...

LandWorks Tightens Integration With Esri in Land Management Software Upgrades

LandWorks Tightens Integration With Esri in Land Management Software Upgrades

MV Products Vacuum Pump Exhaust Filters Remove Oil Mist From Work Environments

MV Products Vacuum Pump Exhaust Filters Remove Oil Mist From Work Environments

Power Engineering

Article Archives for Power Engineering Magazine

Continuing Education

Professional Development Hours

To access a course listing associated to a specific topic listed below, click on the topic of choice from the list below.

Latest Energy Jobs

View more Job Listings >>