Nuclear power unit in Canada generating power for first time in 15 years

Sep 20, 2012

Bruce Power on Sept. 19 successfully synchronized the 750 MW Unit 1 to Ontario’s electricity grid, generating power from the unit for the first time in 15 years.

“This is a significant achievement for Bruce Power and another tangible milestone that the Restart project is nearing completion and we are close to securing eight units of operation,” said Duncan Hawthorne, president and CEO.

With first synchronization now complete, final planned commissioning activities, including safety system shutdown testing, will be carried out on Unit 1. Unit 2 is on track to return to operations in the fourth quarter of 2012.

The return to service of Units 1 and 2 will bring the Bruce Power site back to its eight-unit capacity, doubling the number of operational units from 10 years ago when the company began its multi-year revitalization program to make it the largest nuclear generating facility in the world. Prior to this investment, half of the units on the site were laid up.

Bruce Power’s 2,300-acre site houses the Bruce A and B generating stations, which each hold four CANDU reactors. Prior to the restart of Unit 1, six of those units were operational and producing more than 4,700 MW. The plant generates about 25 percent of Ontario’s electricity.

Subscribe to Nuclear Power International magazine

Sponsored by FLSmidth
Font Sizes:
Recommend this article Recommend this article () You recommended this article You recommended this article ()
Follow Power Engineering on Twitter

Headline News

There is no current content available.

Latest News

Kvaerner awarded contract for gas-fired power plant in Delaware

Kvaerner North American Construction Inc. and its joint venture partner, Parsons Brinckerhoff...

Canadian Solar purchases two solar projects

Canadian Solar Inc. has acquired a majority interest in two utility-scale solar power project...

Operators Restart Unit 2 at PPL Susquehanna

Unit 2 at the PPL Susquehanna nuclear power plant near Berwick, Pa. resumed generating electr...

Settlement agreement limits cost recovery at Edwardsport

The Indiana Utility Regulatory Commission (IURC) on Dec. 27 modified and approved a settlemen...

Toshiba in talks to sell portion of Westinghouse nuclear unit

Toshiba Corp is in talks  to sell up to 16% of its stake in the Westinghouse Electric Co...

Utah nixes nuclear waste storage facility

Plans to park radioactive waste at a storage facility in Utah have been officially called off.

NuScale taps Fluor exec for CEO

The Oregon-based company NuScale has hired former Fluor executive John L. Hopkins to replace ...

Current Magazine Issue

03/01/2013
Volume 117, Issue 3
1303pe-cover

Watch POWER-GEN 2012

Power Engineering

Article Archives for Power Engineering Magazine

Archived Articles

2000 | 2001 | 2002 | 2003 | 2004 | 2005 | 2006 | 2007 | 2008 | 2009 | 2010 | 2011 | 2012 | 2013

Continuing Education

Professional Development Hours

To access a course listing associated to a specific topic listed below, click on the topic of choice from the list below.