Court rules against strike at 11,200 MW Belo Monte hydropower plant

By HydroWorld.com editors

A Brazilian court has ruled that a work stoppage on the country's 11,200 MW Belo Monte hydroelectric project is illegal, South American sources report.

Workers at the hydropower plant went on strike early this past week, demanding improved pay and more time to visit family members, according to Sintrapav, or the Union of Heavy Construction Industry Workers.

A judge in the regional labor court of Para ruled that a contract signed in November between the workers and project operator Norte Energia, also called Consorcio Construtor Belo Monte, is valid through October because its terms were not violated.

The court says the workers will be fined $106,000 per day if they do not return to work.

Arcadis recently signed a deal worth $146 million to join the Norte Energia consortium.

Belo Monte will be the world's third-largest hydroelectric plant when completed and is one of several projects currently being developed in Brazil. Commissioning is scheduled for 2015.

Read more Latin America hydroelectric news

Sponsored by FLSmidth
Font Sizes:
Recommend this article Recommend this article () You recommended this article You recommended this article ()
Follow Power Engineering on Twitter

Latest News

Shutterstock coal production trucks

Weekly Coal Production

The Weekly Coal Production shows how much coal is being produced across the U.S.

Federal Reserve Bank of Dallas Weekly Economic Indicators financial business

The Federal Reserve Bank of Dallas' Economic Indicators

The Federal Reserve Bank of Dallas offers a glimpse into how the markets are doing domestical...

Kvaerner awarded contract for gas-fired power plant in Delaware

Kvaerner North American Construction Inc. and its joint venture partner, Parsons Brinckerhoff...

Canadian Solar purchases two solar projects

Canadian Solar Inc. has acquired a majority interest in two utility-scale solar power project...

Operators Restart Unit 2 at PPL Susquehanna

Unit 2 at the PPL Susquehanna nuclear power plant near Berwick, Pa. resumed generating electr...

Settlement agreement limits cost recovery at Edwardsport

The Indiana Utility Regulatory Commission (IURC) on Dec. 27 modified and approved a settlemen...

Toshiba in talks to sell portion of Westinghouse nuclear unit

Toshiba Corp is in talks  to sell up to 16% of its stake in the Westinghouse Electric Co...

Utah nixes nuclear waste storage facility

Plans to park radioactive waste at a storage facility in Utah have been officially called off.

Current Magazine Issue

04/01/2013
Volume 117, Issue 4
1304pe-cover

Watch POWER-GEN 2012

Power Engineering

Article Archives for Power Engineering Magazine

Archived Articles

2000 | 2001 | 2002 | 2003 | 2004 | 2005 | 2006 | 2007 | 2008 | 2009 | 2010 | 2011 | 2012 | 2013

Continuing Education

Professional Development Hours

To access a course listing associated to a specific topic listed below, click on the topic of choice from the list below.