A federal judge in Brazil on March 30 suspended the construction license of the Teles Pires hydroelectric dam in the Brazilian Amazon, citing violations of the rights of the Kayabi, Apiaká and Mundurucu indigenous peoples.

Célia Regina Ody Bernardes, a federal judge in the state of Mato Grosso, ordered the immediate suspension of all activities in dam construction, "especially explosions of boulders in the region of Sete Quedas (Seven Waterfalls)," cited as an area considered sacred for the Kayabi, Mundurucu and Apiaká peoples, according to a press release.

With an estimated installed capacity of 1,820 MW, the dam has been under construction since August 2011 on the Teles Pires River, a major tributary of the Tapajós River in the heart of the Brazilian Amazon. The dam is one of six large hydro-projects planned for the Teles Pires River, bordering the states of Mato Grosso and Pará.

In her decision, according to InternationalRivers.com, Judge Bernardes concluded that prior to greenlighting dam construction, the federal environmental agency IBAMA failed to consult with affected indigenous communities, despite serious threats to their "socioeconomic and cultural well-being," constituting a violation of the Brazilian Constitution and ILO Convention 169, which Brazil signed in 2004.

Read more Latin America hydropower news

Sponsored by FLSmidth

Related Articles

Brazil Eletrobras Eletronuclear Angra 3 nuclear power plant Areva contract services euros

Areva awarded $89mn contract for nuclear reactor work in Brazil

Areva was awarded a 75 million euros ($89.6 million) contract for the 1,405-MW Angra 3 nuclear power project in Brazil.

SunEdison announces new president of Europe, Africa And Latin America

SunEdison Inc. (NYSE: SUNE), a provider of solar energy services, appointed Jose Perez as president of SunEdison Europe, Africa and Latin America; replacing Pancho Perez.

Follow Power Engineering on Twitter
Latest News

NuScale completes upper module mockup of small nuclear reactor

NuScale Power LLC said it completed fabrication and assembly of a full-scale, upper module mo...

Farley nuclear power plant goes offline for scheduled outage

Workers at the Farley nuclear power plant in Alabama took Unit 1 offline for a scheduled refu...

GE Hitachi Nuclear Energy dedicates reactor training area

GE Hitachi Nuclear Energy (GEH) dedicated its new boiling water reactor under-vessel training...

Shell Chemical nears air permit for 250-MW power project in Pennsylvania

Shell Chemical Appalachia LLC is close to an air permit from the Pennsylvania Department of E...

NRG seeks Texas approval to buy power plant being moved from Mississippi

NRG Texas Power LLC applied March 27 at the Public Utility Commission of Texas for approval o...

VIDEO: One nuclear power steam generator’s trip to the Summer plant site

New video from Westinghouse Electric shows the journey the one steam generator took from the ...

Nation's biggest nuclear firm makes a play for green money

A big player in the troubled nuclear power industry is trying to change the rules of the ener...

Emerson awarded $76mn ultrasupercritical coal-fired automation project

Emerson Process Management, a subsidiary of Emerson (NYSE: EMR), was awarded a $76 million co...

Power Engineering Current Issue

02/01/2015
Volume 119, Issue 2
1502PE-cover
Products Showcase
Dynamic Fluoride Ion cleaning DFIC of industrial natural gas turbines Hi-Tech Furnace Systems

Dynamic Fluoride Ion Cleaning of IGT Parts

The Dynamic Fluoride Ion Cleaning (DFIC) Process from Hi-Tech Furnace Systems is able to clean deep, narrow cracks of oxides by cycling between negative, atmospheric, and positive pressure.

Archived Articles

2000 | 2001 | 2002 | 2003 | 2004 | 2005 | 2006 | 2007 | 2008 | 2009 | 2010 | 2011 | 2012 | 2013 | 2014 | 2015

Power Industry Wire News

Yuma Energy, Inc. Announces 2014 Financial Results and Provides an Operational Overview

Yuma Energy, Inc. Announces 2014 Financial Results and Provides an Operational Overview

DEKRA to Present New Algorithm for Faster and More Reliable Advanced Driver Assistance Systems at SAE 2015 World Congress

DEKRA to Present New Algorithm for Faster and More Reliable Advanced Driver Assistance ...

Dozens of Local Companies to Participate at Converters Expo in the Heart of Green Bay

Dozens of Local Companies to Participate at Converters Expo in the Heart of Green Bay

Clear Measure Names Chief Architect, Hires Principal Software Engineers

Clear Measure Names Chief Architect, Hires Principal Software Engineers

Save the Date: 8th Annual Whale Shark Festival Announced for Isla Mujeres

Save the Date: 8th Annual Whale Shark Festival Announced for Isla Mujeres

Power Engineering

Article Archives for Power Engineering Magazine

Continuing Education

Professional Development Hours

To access a course listing associated to a specific topic listed below, click on the topic of choice from the list below.

Latest Energy Jobs

View more Job Listings >>