Alstom said it has been awarded a contract worth approximately €50 million ($64.2 million) by utility Hydro-Québec to update the Robert-Bourassa generating facility in Canada.

Consisting of 16 units with a total power generation capacity of 5,616 MW, Alstom said Centrale Robert-Bourassa is the world’s largest underground generating station.

Under the terms of the contract, Alstom will design, manufacture and deliver four new 333 MW Francis turbine runners for units 1-4 of the dam, and carry out the complete refurbishment and modernization of two turbine-generator groups. Alstom will also supply several new components - ring gate, distributor, servomotors and turbine shaft - for unit 1 of the power plant, while refurbishing some of the existing components for units 2 and 3, and replacing 16 electronic governor systems.

The contract also includes an option for the supply of four more runners for units 4-8 and the refurbishment and modernization of six more turbine-generator units.

Commissioning of the first upgraded unit is scheduled for autumn 2013.

Read more hydroelectric news

Recommend this article Recommend this article () You recommended this article You recommended this article ()
Follow Power Engineering on Twitter

Power Engineering

Article Archives for Power Engineering Magazine