Unit 1 to be fitted with roof

06/28/2011

Tokyo Electric Power Co. (TEPCO) began constructing a temporary airtight structure to cover the exposed roof of Unit 1 at the Fukushima Daiichi nuclear power plant. A buildup of hydrogen caused an explosion that blew the roof off of the unit in March, sending radioactive material into the air.

The roof is expected to be complete by August and last two or three years, according to news reports. It is designed to prevent rainwater from entering, and potentially leaking out from, the building. TEPCO reportedly said the covering is not radiation-proof, but will stop some radiation from being carried out.

Reports said the cover is made of a polyester fabric with a vinyl chloride resin coating supported by a steel frame 154 feet wide and 177 feet tall. A pair of 750-ton cranes with lead-lined cabins to protect the operators from radiation that still is being emitted from the reactor will install the cover.

Unit 1 was given priority because most of the building’s original roof collapsed into the structure. That makes it easier to maneuver cranes around its perimeter, news reports said.

Subscribe to Nuclear Power International

Sponsored by FLSmidth
Font Sizes:
Recommend this article Recommend this article () You recommended this article You recommended this article ()
Follow Power Engineering on Twitter

Headline News

There is no current content available.

Latest News

Shutterstock coal production trucks

Weekly Coal Production

The Weekly Coal Production shows how much coal is being produced across the U.S.

Federal Reserve Bank of Dallas Weekly Economic Indicators financial business

The Federal Reserve Bank of Dallas' Economic Indicators

The Federal Reserve Bank of Dallas offers a glimpse into how the markets are doing domestical...

Kvaerner awarded contract for gas-fired power plant in Delaware

Kvaerner North American Construction Inc. and its joint venture partner, Parsons Brinckerhoff...

Canadian Solar purchases two solar projects

Canadian Solar Inc. has acquired a majority interest in two utility-scale solar power project...

Operators Restart Unit 2 at PPL Susquehanna

Unit 2 at the PPL Susquehanna nuclear power plant near Berwick, Pa. resumed generating electr...

Settlement agreement limits cost recovery at Edwardsport

The Indiana Utility Regulatory Commission (IURC) on Dec. 27 modified and approved a settlemen...

Toshiba in talks to sell portion of Westinghouse nuclear unit

Toshiba Corp is in talks  to sell up to 16% of its stake in the Westinghouse Electric Co...

Utah nixes nuclear waste storage facility

Plans to park radioactive waste at a storage facility in Utah have been officially called off.

Current Magazine Issue

03/01/2013
Volume 117, Issue 3
1303pe-cover

Watch POWER-GEN 2012

Power Engineering

Article Archives for Power Engineering Magazine

Archived Articles

2000 | 2001 | 2002 | 2003 | 2004 | 2005 | 2006 | 2007 | 2008 | 2009 | 2010 | 2011 | 2012 | 2013

Continuing Education

Professional Development Hours

To access a course listing associated to a specific topic listed below, click on the topic of choice from the list below.