U.S. Geothermal Services, a unit of U.S. Geothermal Inc., signed a $1.65 million agreement with Raft River Energy I LLC to repair two production wells at Unit 1 of the Raft River project.

USG Services will fund and manage the repairs of production wells RRG-2 and RRG-7. RRG-2 was shut down in June 2010 after a pump failure. RRG-7 has a leak in a cement seal that failed where two steel casing sections overlap, allowing cooler geothermal fluid to enter the well bore.

The flowing production temperature in RRG-7 declined from 299 degrees F to 240 degrees F over the past two years. A pump rig was mobilized to the Raft River site on May 16 and began working on well RRG-2. Once the repairs are complete, the plant’s annual average output is expected to increase 25 percent from 8 MW annual average to around10 MW.

In addition to the repairs, a flow stimulation technique called deflagration will be applied to wells RRG-2 and RRG-7 which may increase fluid flow from the known production zones.

Read more geothermal energy news

Recommend this article Recommend this article () You recommended this article You recommended this article ()
Follow Power Engineering on Twitter

Power Engineering

Article Archives for Power Engineering Magazine