2 December 2009-- Exelon Power said it plans to retire two coal-fired units and shut down a plant, all in Pennsylvania, starting in 2011.

The company said the 345 MW Cromby Generating Station and Units 1 and 2 at Eddystone Generating Station would be shut down. After the retirements, Eddystone will continue to operate 820 MW of generating capacity.

Cromby Unit 1 is a 144 MW coal-fired unit and Unit 2 is a 201 MW unit that operates on either natural gas or No. 6 fuel oil. Both units will be retired, ultimately shutting down the entire plant. Eddystone is losing 588 MW of capacity.

"Decreased power demand, over supply of natural gas and increasing operating costs, has led Exelon Power to retire these units," said Doyle Beneby, senior vice president of Exelon Power.

"Only the most efficient and lowest cost units can consistently compete in the wholesale markets. Unfortunately, these aging units are no longer efficient enough to compete with newer resources," said Beneby. "These units faced a difficult year economically in 2009 and we expect the forces that contributed to the difficulties to continue for an extended period of time. Those forces include increasing capital expenditures and decreased demand for electricity."

Cromby Generating Station is on the Schuylkill River in Phoenixville, Pa. Cromby Unit 1 and Unit 2 were placed in service in 1954 and 1955, respectively. Unit 1 is a 144 MW coal-fired unit. Unit 2 is a 201 MW unit that operates on either natural gas or No. 6 fuel oil.

Eddystone Generating Station is on the Delaware River in Eddystone, Pa. Unit 1 is a 279 MW coal-fired unit and Unit 2 is a 309 MW coal-fired unit. Both were placed in service in 1960. Two 380 MW peaking units that run on either natural gas or oil and four oil-burning units that produce a total of 60 MW will continue to be available for operation.

The PJM Interconnection said it will see if the shutdowns will create reliability issues.
Want more news? Subscribe to the FREE E-newsletter!

Sponsored by FLSmidth
Font Sizes:
Recommend this article Recommend this article () You recommended this article You recommended this article ()
Follow Power Engineering on Twitter

Latest News

Shutterstock coal production trucks

Weekly Coal Production

The Weekly Coal Production shows how much coal is being produced across the U.S.

Federal Reserve Bank of Dallas Weekly Economic Indicators financial business

The Federal Reserve Bank of Dallas' Economic Indicators

The Federal Reserve Bank of Dallas offers a glimpse into how the markets are doing domestical...

Kvaerner awarded contract for gas-fired power plant in Delaware

Kvaerner North American Construction Inc. and its joint venture partner, Parsons Brinckerhoff...

Canadian Solar purchases two solar projects

Canadian Solar Inc. has acquired a majority interest in two utility-scale solar power project...

Operators Restart Unit 2 at PPL Susquehanna

Unit 2 at the PPL Susquehanna nuclear power plant near Berwick, Pa. resumed generating electr...

Settlement agreement limits cost recovery at Edwardsport

The Indiana Utility Regulatory Commission (IURC) on Dec. 27 modified and approved a settlemen...

Toshiba in talks to sell portion of Westinghouse nuclear unit

Toshiba Corp is in talks  to sell up to 16% of its stake in the Westinghouse Electric Co...

Utah nixes nuclear waste storage facility

Plans to park radioactive waste at a storage facility in Utah have been officially called off.

Current Magazine Issue

04/01/2013
Volume 117, Issue 4
1304pe-cover

Watch POWER-GEN 2012

Power Engineering

Article Archives for Power Engineering Magazine

Archived Articles

2000 | 2001 | 2002 | 2003 | 2004 | 2005 | 2006 | 2007 | 2008 | 2009 | 2010 | 2011 | 2012 | 2013

Continuing Education

Professional Development Hours

To access a course listing associated to a specific topic listed below, click on the topic of choice from the list below.