Cook Nuclear 1 return-to-service date expected in November

24 October 2008 -- Initial inspections and disassembly of the main turbine are complete at American Electric Power's 1,030 MW Cook Nuclear Plant Unit 1, out of service since Sept. 20 after vibrations -- likely caused by a broken low pressure turbine blade -- damaged the main turbine.

The turbine rotors and other major components have been shipped to the original manufacturers for engineering analysis and repair.

AEP expects to have a return-to-service schedule and cost estimates for the nuclear power unit by late November.

The vibration also caused a hydrogen leak, resulting in a fire in the main generator that caused minimal damage to the facility, which is located in Michigan.

Cook Unit 1 has three low-pressure turbines manufactured by Siemens and one General Electric high-pressure turbine and main generator.

The low-pressure turbine rotors, casings and other support equipment were shipped to the Siemens turbine facility in Charlotte, N.C., to determine whether the components will be repaired or replaced.

The high-pressure turbine rotor was shipped to a General Electric facility in Chicago and is undergoing similar assessments.

Disassembly of the main generator is also complete. The generator rotor will be shipped to the GE facility in Chicago for testing and repair.

Initial electrical testing of the generator rotor and stator has not detected any major issues. Generator parts, such as high voltage bushings and current transformers damaged during the event have been ordered.

At the site, AEP personnel have developed a schedule for the remaining inspections and completion of repairs on other plant equipment such as associated turbine piping and insulation, turbine bearings and turbine plant motors and pumps.

In addition, cleaning of broken insulation in the turbine building, water from fire suppression and oil released from the turbine lube oil system during the event will be done. The oil was contained within plant systems during the event resulting in no impact to the environment.

Siemens and GE are working to deliver parts and perform repairs. Once parts delivery and repair estimates are completed, they will be integrated into the plant schedule and AEP will release a return to service timeline and total cost estimate.

Stories of interest:

AEP's Cook Nuclear Plant Unit 2 briefly enters emergency plan for internal filter leak

AEP's Cook Nuclear Plant Unit 1 briefly enters emergency plan during refueling

Sponsored by FLSmidth

Related Articles

Fuel Tech receives air pollution control contracts worth $3.6Mn

Fuel Tech Inc. has received multiple air pollution control (APC) contracts, worth approximately $3.6 million, from customers in China, Europe and the U.S.

Duke Energy completes ash excavation at W.S. Lee Steam Station

Duke Energy (NYSE: DUK) has submitted filings, to state regulators, outlining additional ash excavation plans for its W.S. Lee Steam Station in Belton, South Carolina.

Follow Power Engineering on Twitter
Latest News
Plant Vogtle construction costs down in first half 2015

Plant Vogtle nuclear expansion spending down in first half of 2015

Georgia Power said in a report that the utility estimates it will spend less on construction ...
Renewable energy developer Cypress Creek Renewables building 2 utility-scale solar farms in South Carolina

Renewable energy developer Cypress Creek Renewables building 2 utility-scale solar farms in South Carolina

Cypress Creek Renewables is investing more than $20 million in new projects in South Carolina.
The Nuclear Regulatory Commission on Thursday cited a

US regulators, Millstone nuke plant settle dispute

The parent company of Connecticut's nuclear plant and federal regulators have reached a settl...
Duke Energy is looking to bring 53 MW of utility-scale solar capacity to the company’s South Carolina service areas by the end of 2016.

Duke Energy launching solar-generating program for South Carolina customers

Duke Energy is looking to bring 53 MW of utility-scale solar capacity to the company’s South ...
The state Department of Natural Resources says historic amounts of oil and natural gas are being produced by Ohio shale wells.

State says Ohio oil, natural gas production at historic high

The state Department of Natural Resources says historic amounts of oil and natural gas are be...
MidAmerican Energy says it will build its next two wind farms in northwest Iowa.

MidAmerican Energy building Iowa wind farms for $900 million

MidAmerican Energy says it will build its next two wind farms in northwest Iowa.

Semprius, Inc. awarded $2.9 million to develop low-cost, solar-generated electricity

Semprius awarded $2.9 million from ARPA-E to develop hybrid solar technology

Semprius, Inc., an innovator in high concentration photovoltaic (HCPV) solar modules, has bee...
08/26 Henry Hub Average Natural Gas Spot Prices

08/26 Henry Hub Average Natural Gas Spot Prices

The Henry Hub is the pricing point for natural gas futures contracts traded on the New York M...

Power Engineering Current Issue

03/01/2014
Volume 118, Issue 3
1403PE-cover
Products Showcase
Dynamic Fluoride Ion cleaning DFIC of industrial natural gas turbines Hi-Tech Furnace Systems

Dynamic Fluoride Ion Cleaning of IGT Parts

The Dynamic Fluoride Ion Cleaning (DFIC) Process from Hi-Tech Furnace Systems is able to clean deep, narrow cracks of oxides by cycling between negative, atmospheric, and positive pressure.

Archived Articles

2000 | 2001 | 2002 | 2003 | 2004 | 2005 | 2006 | 2007 | 2008 | 2009 | 2010 | 2011 | 2012 | 2013

Buyers Guide Categories

Buyers Guide Product Listings

Predictive Maintenance

IPS field service technicians use state-of-the-...

Mitsubishi Gas Turbines

Mitsubishi's advanced turbine technology includ...

Condition Monitoring

TIGER® Monitoring System automates the knowledg...

Turbine Services Limited

Turbine Services Limited, a wholly owned subsid...
Power Industry Wire News

PyroGenesis Canada Inc. to Present at the 4th Annual Liolios Gateway Conference on September 10, 2015

PyroGenesis Canada Inc. to Present at the 4th Annual Liolios Gateway Conference on Sept...

American Power Group Announces Completion of a $3.25 Million Term Loan for the Purchase of Next Generation Natural Gas Flare Capture and Recovery Systems

American Power Group Announces Completion of a $3.25 Million Term Loan for the Purchase...

Anpath Group Signs Merger Agreement With Q2Power

Anpath Group Signs Merger Agreement With Q2Power

Cimation Selected by Shell for Global Cybersecurity Program Roll-Out

Cimation Selected by Shell for Global Cybersecurity Program Roll-Out

Nuclear, LNG Export Projects Dominate Top 10 Capital-Spending Plans in U.S. Southeast Region, an Industrial Info News Alert

Nuclear, LNG Export Projects Dominate Top 10 Capital-Spending Plans in U.S. Southeast R...

Power Engineering

Article Archives for Power Engineering Magazine

Continuing Education

Professional Development Hours

To access a course listing associated to a specific topic listed below, click on the topic of choice from the list below.

Latest Energy Jobs

View more Job Listings >>