16 coal-fired power plant proposals scrapped

Plans for constructing 16 coal-fired power plants around the country have been scrapped and three dozen more face delays, all as a result of uncertain construction costs and emissions regulations issues.

According to a report by the US Department of Energy (DOE), eight coal-fired plants have been cancelled since May. That was on top of the eight plants that were slated for construction in Texas earlier this year. Combined, the sixteen plants would have produced 13,684 MW of power. The DOE also said that an additional 32,000 MW of coal-generated power plants were being delayed.

Utilities' plans were also stymied by rising material costs and shortages of skilled construction labor

The DOE says that 121 power plant proposals are still viable, but since 2002, only 15 plants were built that produce only 3,700 MW of total combined power.

Sponsored by FLSmidth

Related Articles

EPA unveils SO2 scrubber-reliant haze plan for Texas

The U.S. Environmental Protection Agency is proposing new regional haze SO2 reduction requirements for Texas based on a series of presumed scrubber installations and scrubber upgrades on 14 coal-fired power plant units.

National Grid joins proposal for 300-mile cable in Maine

Utility giant National Grid is partnering with a company that specializes in underwater cable projects in an alliance seeking to build a 300-mile cable to bring Canadian hydropower and Maine wind power to Greater Boston to help meet the energy needs of power-hungry southern New England, the companies announced Tuesday.

Follow Power Engineering on Twitter
Latest News

MHPS to supply M501J gas, steam turbines to new combined-cycle power plant in Korea

Mitsubishi Hitachi Power Systems (MHPS), jointly with Marubeni Corp., has received an order f...

Business leaders throw support behind coal plant proposal

Business leaders on Thursday outlined the economic devastation they say could come if New Mex...

TVA seeks public comment for future coal ash storage at Bull Run

The Tennessee Valley Authority (TVA) is asking for public input on plans to expand dry onsite...

California Public Utilities Commission Approves NRG Energy’s Carlsbad Energy Center

California Public Utilities Commission (CPUC) has approved the SDG&E Power Purchase and T...

Vermont joins international effort to fight climate change

Gov. Peter Shumlin says Vermont has signed on to what he called a first-of-its-kind agreement...

Products May 2015

Callaway Energy Center's Replacement Reactor Vessel Closure Head Project

Replacing heavy equipment is one way utilities can extend the life and increase the reliabili...

Managing CCRs and Process Water: Why Handling Bottom Ash Wet May Remain The Best Option

The U.S. coal-fired electric generation industry once again finds itself in the crosshairs of...

Power Engineering Current Issue

03/01/2014
Volume 118, Issue 3
1403PE-cover
Products Showcase
Dynamic Fluoride Ion cleaning DFIC of industrial natural gas turbines Hi-Tech Furnace Systems

Dynamic Fluoride Ion Cleaning of IGT Parts

The Dynamic Fluoride Ion Cleaning (DFIC) Process from Hi-Tech Furnace Systems is able to clean deep, narrow cracks of oxides by cycling between negative, atmospheric, and positive pressure.

Archived Articles

2000 | 2001 | 2002 | 2003 | 2004 | 2005 | 2006 | 2007 | 2008 | 2009 | 2010 | 2011 | 2012 | 2013

Power Industry Wire News

MIC President Marybeth Miceli Named to AATA Board of Directors; AATA to Provide Free NDT Job Training to Vets, Disadvantaged Young Adults

MIC President Marybeth Miceli Named to AATA Board of Directors; AATA to Provide Free ND...

Alexium Anticipates Potential Addressable Revenue of More Than US$10M for 2015

Alexium Anticipates Potential Addressable Revenue of More Than US$10M for 2015

Upcoming Greenhouse Webinar Teaches Companies How to Engage Engineers in Hiring Top Tech Talent

Upcoming Greenhouse Webinar Teaches Companies How to Engage Engineers in Hiring Top Tec...

Perma-Fix Environmental Services to Present at the Marcum MicroCap Conference

Perma-Fix Environmental Services to Present at the Marcum MicroCap Conference

Blue Earth Receives Notice From NASDAQ That the Company Is No Longer Subject to a Possible Delisting

Blue Earth Receives Notice From NASDAQ That the Company Is No Longer Subject to a Possi...

Power Engineering

Article Archives for Power Engineering Magazine

Continuing Education

Professional Development Hours

To access a course listing associated to a specific topic listed below, click on the topic of choice from the list below.

Latest Energy Jobs

View more Job Listings >>