Energy East to upgrade hydroelectric plants

6 April 2007 -- Energy East Corp.'s subsidiary Rochester Gas and Electric Corp. plans to invest more than $20 million over the next three years in its Station 2 and Station 5 hydroelectric plants on the Genesee River in Rochester. The investment will result in additional generating capacity of 9 MW at the two plants that currently have a combined generating capacity of approximately 49 MW.

Most of the work will take place at Station 2 at High Falls. Planning will begin in 2007 to double the size of the facility and its current 6.5 MW generating capacity. This work is expected to be complete in 2009. In addition, the existing generator at the plant will be rewound to make it more efficient, netting an additional generating capacity of 1 MW. This work will be done in 2008.

RG&E also plans to rewind a generator and complete related work at Station 5 at Middle/Lower Falls next summer. This project will add approximately 1.5 MW of generating capacity at the plant.

Sponsored by FLSmidth

Related Articles

Energy-Pipeline Operator Upgrades to Open-Architecture Reciprocating Engines Control

Electricity and natural-gas delivery company CenterPoint Energy – Mississippi River Transmission LLC (CNP-MRT) owns and operates 8,200 miles of transmission pipeline that carried 1.6 trillion cubic feet of gas throughout a nine-state, mid-continent region during 2012.

Arizona Public Service APS Cholla coal-fired power plant Environmental Protection Agency EPA Four Corners Ocotillo New Mexico

APS proposes closing three coal-fired units by 2020

Arizona Public Service said it would close a coal-fired unit and shut down two others by mid-2020 as part of a compromise with the U.S. Environmental Protection Agency.

Follow Power Engineering on Twitter
Latest News
08/29 Weekly Coal Production Report EIA

08/29 Weekly Coal Production Report

The Weekly Coal Production Report has been updated for the week ended Aug 29, 2015.

Dungeness B nuclear reactor online after planned outage

Dungeness B nuclear reactor online after planned outage

The Dungeness B nuclear Unit 22 is back online following a 16-week planned maintenance outage.
Eletrobras suspends nuclear construction contract amid corruption probe

Eletrobras suspends nuclear construction contract amid corruption probe

Eletrobras said it would suspend a contract with a consortium that is building the 1,405-MW t...
Alabama Public Service Commission OKs construction of renewable energy generation projects

Alabama regulators OK construction of renewable energy generation projects

In a 3-0 vote, the Alabama Public Service Commission approved a proposal from Alabama Power t...
NRC to increase oversight of Pilgrim nuclear power plant

NRC to increase oversight of Pilgrim nuclear power plant

The U.S. Nuclear Regulatory Commission (NRC) will increase its oversight of the 670-MW Pilgri...
Kettleman utility-scale solar project providing electricity to Silicon Valley city of Palo Alto

Kettleman utility-scale solar project powering city of Palo Alto

The Kettleman Solar Power Project in Kings County was built on about 264 acres of land on Hig...
Areva delivers reactor vessel head to Belgium nuclear power plant

Areva delivers reactor vessel head to Belgium nuclear power plant

Areva delivered a nuclear reactor vessel head to Electrabel for Unit 4 at the Doel nuclear po...
EPSA files brief with Supreme court on FERC demand response case

EPSA files brief with Supreme Court on FERC demand response case

The Electric Power Supply Association (EPSA) and a number of other parties filed a legal brie...

Power Engineering Current Issue

03/01/2014
Volume 118, Issue 3
1403PE-cover
Products Showcase
Areva delivers reactor vessel head to Belgium nuclear power plant

Areva delivers reactor vessel head to Belgium nuclear power plant

Areva delivered a nuclear reactor vessel head to Electrabel for Unit 4 at the Doel nuclear power plant in Belgium.

GE announces launch of latest aeroderivative gas turbine, LM6000-PF+

GE announces launch of latest aeroderivative gas turbine, LM6000-PF+

GE is launching its latest aeroderivative gas turbine, the LM6000-PF+, which employs technologies from four GE businesses, bringing power online faster and more efficiently than ever before.

Dynamic Fluoride Ion cleaning DFIC of industrial natural gas turbines Hi-Tech Furnace Systems

Dynamic Fluoride Ion Cleaning of IGT Parts

The Dynamic Fluoride Ion Cleaning (DFIC) Process from Hi-Tech Furnace Systems is able to clean deep, narrow cracks of oxides by cycling between negative, atmospheric, and positive pressure.

Archived Articles

2000 | 2001 | 2002 | 2003 | 2004 | 2005 | 2006 | 2007 | 2008 | 2009 | 2010 | 2011 | 2012 | 2013

Buyers Guide Product Listings

Pipeline Repair and Rehabilitation

Tyfo® Fibrwrap® Pipe Rehabilitation System is a...

RETROFIT

Braden's retrofit strengths are divided into tw...
Power Industry Wire News

Energy Partner Paul Kaufman Joins Sheppard Mullin Del Mar

Energy Partner Paul Kaufman Joins Sheppard Mullin Del Mar

Algae Biomass Summit Showcases Advances in Engineering and Analysis

Algae Biomass Summit Showcases Advances in Engineering and Analysis

Dais Looks to Further Build on Aqualyte V4 Following Strong Performance and Improved AHRI Certification Results of Aqualyte V3

Dais Looks to Further Build on Aqualyte V4 Following Strong Performance and Improved AH...

Energy Marketing Conference for Retailers Selects Good Energy as Panel Moderator

Energy Marketing Conference for Retailers Selects Good Energy as Panel Moderator

UGE and OTEPI Continue Success in Panama by Providing Solar to Mega Storage

UGE and OTEPI Continue Success in Panama by Providing Solar to Mega Storage

Power Engineering

Article Archives for Power Engineering Magazine

Continuing Education

Professional Development Hours

To access a course listing associated to a specific topic listed below, click on the topic of choice from the list below.

Latest Energy Jobs

View more Job Listings >>