23 December 2005 - Alstom has won contracts worth over €200m ($237m) for the supply of equipment and services for the Afam VI combined cycle power plant project at Port Harcourt, Nigeria.
Alstom will supply 3 GT13E2 gas turbines (167 MW each) and auxiliary equipment to the Korean firm Daewoo E&C Co. Ltd, in charge of the engineering, procurement and construction, for the end customer Shell Petroleum Development Company (SPDC).
Under a separate agreement signed with SPDC, Alstom will provide long-term operation support and maintenance services for the gas turbines and generators. It will also provide initial technical support to help set up a service organization at the site.