Appeals court overturns decision on Nova Scotia Power's tax case

HALIFAX, Jan. 28, 2003 -- Nova Scotia Power Inc. (NSPI) said Monday it is seeking leave to appeal to the Supreme Court of Canada the recent Federal Court ruling that overturned a Tax Court of Canada decision in the company's favor. Nova Scotia Power is a wholly owned subsidiary of Emera Inc.

The case arose when NSPI claimed deductions related to capitalized interest on assets constructed by its predecessor, Nova Scotia Power Corporation (NSPC). The assets were purchased by NSPI in the course of privatizing NSPC in 1992. The deductions created substantial tax depreciation that was used to reduce income taxes payable by approximately $130 million through 2002.

The Canada Customs and Revenue Agency (CCRA) disallowed the deductions claimed, and NSPI pursued the issue successfully through the Tax Court. CCRA appealed the decision to the Federal Court of Appeal, which has overturned the January 2002 Tax Court ruling.

"We are disappointed with this decision," said David Mann, President and Chief Executive Officer of Nova Scotia Power. "We will seek leave to appeal to the Supreme Court of Canada."

Nova Scotia Power will work with its regulator, the Nova Scotia Utility and Review Board to determine an appropriate mechanism to recover the costs of these taxes should the appeal process prove unsuccessful.

The total potential liability through 2002 is approximately $160 million, including interest charges. The company expects to deposit the balance with CCRA in the near future to avoid further interest charges. The total payment will be recoverable should the issue be finally resolved in the company's favor.

About Emera Inc.

Emera Inc. (EMA-TSX) is a diversified energy and services company, with 550,000 customers and $4.0 billion in assets. The company has two wholly-owned regulated electric utility subsidiaries, Nova Scotia Power Inc. and Bangor Hydro-Electric Company.

Nova Scotia Power supplies over 95% of the electric generation, transmission and distribution in Nova Scotia. Bangor Hydro provides electricity transmission and distribution service to 110,000 customers in eastern Maine. It is a member of the New England Power Pool, and is interconnected with the other New England utilities to the south and with New Brunswick Power to the north.

In addition, Emera Energy manages Emera's growing gas infrastructure investment portfolio, including its 12.5% interest in the Maritimes & Northeast Pipeline, which delivers Sable natural gas to markets in Maritime Canada and the northeastern United States; and an 8.4% interest in the Sable Offshore Energy Project offshore platforms and sub-sea field gathering lines. Emera Energy also incorporates Emera Energy Services, Emera Fuels, and Emera's business development activities. Visit Emera on the web at www.Emera.com.

Sponsored by FLSmidth

Related Articles

The Blockbuster Conundrum

Remember Blockbuster Video? Not too many years ago, Blockbuster was a business titan.

Gaelectric pursues FERC complaint over 460-MW wind project

The Federal Energy Regulatory Commission on April 29 will publish in the Federal Register a notice seeking comment on a complaint filed April 21 against NorthWestern Corp. by the developer of a 460-MW wind farm project in Montana.

Follow Power Engineering on Twitter
Latest News

PNM files ownership plan, coal supply deal with regulators

New Mexico's largest electric provider says it's on track to meeting a deadline for submittin...

Oklahoma attorney general challenges EPA's clean-air plan

A plan by the U.S. Environmental Protection Agency to reduce emissions from coal-fired power ...

Wave Energy Week will mix marine energy developers with traditional hydropower

Oregon Gov. Kate Brown, Democrat, has proclaimed “July 13-17, 2015 to be Oregon Wave Week in ...

Public Service Company of Oklahoma seeks rate increase

Public Service Company of Oklahoma is asking for a 13.6 percent rate increase it says is need...

GAO looks at reliability impacts of changing power generation mix

The Government Accountability Office (GAO) on June 29 released a study provided a month befor...

On the day after MATS decision, Bernstein sees only a limited reprieve for coal units

In light of the U.S. Supreme Court ruling against the EPA's Mercury and Air Toxics Standards ...

Pence says Indiana will not comply with coal plant regulations

Indiana will not comply with President Barack Obama's plan to battle climate change by requir...

Westermost Rough offshore wind park enters operations

The 210-MW offshore wind power plant, Westermost Rough, has entered operations. The project w...

Power Engineering Current Issue

01/01/2015
Volume 119, Issue 1
1501pe-cover-lg
Products Showcase
Dynamic Fluoride Ion cleaning DFIC of industrial natural gas turbines Hi-Tech Furnace Systems

Dynamic Fluoride Ion Cleaning of IGT Parts

The Dynamic Fluoride Ion Cleaning (DFIC) Process from Hi-Tech Furnace Systems is able to clean deep, narrow cracks of oxides by cycling between negative, atmospheric, and positive pressure.

Archived Articles

2000 | 2001 | 2002 | 2003 | 2004 | 2005 | 2006 | 2007 | 2008 | 2009 | 2010 | 2011 | 2012 | 2013 | 2014 | 2015

Buyers Guide Categories

Buyers Guide Product Listings

Transmission Services

Blattner Energy is a diversified electrical gen...

Sargent & Lundy Engineering & Design Services

Our experience and capabilities for power deliv...
Power Industry Wire News

NW Natural Announces Dividend and Schedules Conference Call to Review Results for the Three and Six Months Ended June 30, 2015

NW Natural Announces Dividend and Schedules Conference Call to Review Results for the T...

Vantage Drilling Responds to News Reports Regarding Petrobras

Vantage Drilling Responds to News Reports Regarding Petrobras

National Grid Drives Innovation Through REV Demonstration Projects

National Grid Drives Innovation Through REV Demonstration Projects

Cardinal Resources' $28.8 Million Cameroon Red Bird Contract Advances; Company Expects Financing Completed, Implementation, in Q3-15

Cardinal Resources' $28.8 Million Cameroon Red Bird Contract Advances; Company Expects ...

Letter From CGE Energy (McKenzie Bay Intl.) President Bryan Zaplitny

Letter From CGE Energy (McKenzie Bay Intl.) President Bryan Zaplitny

Power Engineering

Article Archives for Power Engineering Magazine

Continuing Education

Professional Development Hours

To access a course listing associated to a specific topic listed below, click on the topic of choice from the list below.

Latest Energy Jobs

View more Job Listings >>