Duke/Fluor Daniel to build 875-MW power plant for South Carolina Electric & Gas

CHARLOTTE, N.C., Feb. 5, 2002 -- Duke/Fluor Daniel (D/FD) has been awarded a contract by South Carolina Electric & Gas Company (SCE&G) to perform engineering, procurement and construction (EPC) services for an 875-megawatt, natural gas- and oil-fired power plant in Jasper County, S.C.

The project will feature three General Electric 7FA combustion turbines, one Alstom steam turbine for highly efficient "combined-cycle" power generation and will include selective catalytic reduction technology to provide for reduced nitrogen oxides in plant emissions. Commercial operation is scheduled for summer 2004.

Peak employment during construction is expected to top 800 workers. The value of the D/FD contract was not disclosed.

"Duke/Fluor Daniel has really helped move this project forward," said Neville Lorick, president -- SCE&G. "Prior to construction we determined that demand growth called for us to expand our original plan for a 600-megawatt facility to provide for an 875-megawatt plant. D/FD helped make that happen quickly and effectively. This will enable us to deliver economies of scale and other economic benefits to our customers."

"All of us at Duke/Fluor Daniel really appreciate the continuing confidence that SCE&G places in our work," said Jeff Faulk, president and chief executive officer of Duke/Fluor Daniel. "Our relationship goes back more than a decade, to when we began work on the Cope Generating Station. We've continued to work together on the Urquhart repowering project and now the Jasper County facility."

In 1996, D/FD completed turnkey environmental, permitting, engineering, procurement, construction and start-up services for SCE&G's Cope Generating Station, a 385-megawatt coal- and natural gas-fired power plant in Cope, S.C. In 2000, D/FD was awarded a contract to provide turnkey EPC services for the Urquhart Station Repowering Project, which will result in a 450-megawatt, natural gas-fired, combined-cycle power plant in Aiken County, S.C.

SCE&G is a subsidiary of SCANA Corporation, a Fortune 500 energy-based holding company headquartered in Columbia, S.C. SCE&G provides electric service to more than 540,000 customers in 24 central and southern counties in South Carolina.

Duke/Fluor Daniel provides comprehensive engineering, procurement, construction, commissioning and operating plant services for fossil-fueled electric power generating facilities worldwide. The partnership of Duke Energy and Fluor Corporation affiliates is one of the largest power contractors in the world and has the largest U.S. market share for the engineering and construction of natural gas-fired power projects. D/FD operating plant services supports utility, merchant and cogeneration plants, including operations and maintenance contracts, capital projects, turbine fleet management, environmental retrofits and other major plant improvements. For more information visit www.dukefluordaniel.com.

Fluor Corporation provides services on a global basis in the fields of engineering, procurement, construction, operations, maintenance and project management. For more information visit www.fluor.com.

Duke Energy, a diversified multinational energy company, creates value for customers and shareholders through an integrated network of energy assets and expertise. More information about the company is available on the Internet at: www.duke-energy.com.


Sponsored by FLSmidth

Related Articles

Energy-Pipeline Operator Upgrades to Open-Architecture Reciprocating Engines Control

Electricity and natural-gas delivery company CenterPoint Energy – Mississippi River Transmission LLC (CNP-MRT) owns and operates 8,200 miles of transmission pipeline that carried 1.6 trillion cubic feet of gas throughout a nine-state, mid-continent region during 2012.

Arizona Public Service APS Cholla coal-fired power plant Environmental Protection Agency EPA Four Corners Ocotillo New Mexico

APS proposes closing three coal-fired units by 2020

Arizona Public Service said it would close a coal-fired unit and shut down two others by mid-2020 as part of a compromise with the U.S. Environmental Protection Agency.

Follow Power Engineering on Twitter

Latest News

 MS Power coal-to-gas conversion nearly complete

MS Power coal-to-gas conversion nearly complete

A coal-to-gas conversion project at a power plant operated by Mississippi Power is nearly com...
 North Anna nuclear power plant shuts down

North Anna nuclear power plant shuts down

Unit 1 of the North Anna nuclear power plant automatically tripped offline Feb. 26 as workers...
 Oklahoma leaders looking for more wind regulations

Oklahoma leaders looking for more wind regulations

With wind energy production in full swing in Oklahoma, legislative leaders are looking to imp...

Second-oldest nuclear reactor in S. Korea OK to restart

South Korea’s nuclear watchdog approved a plan to restart a 679-MW nuclear power unit that wa...
 SunEdison to bring power to 20Mn people by 2020

Video: SunEdison to bring power to 20Mn people by 2020

SunEdison, Inc. (NYSE: SUNE) announced plans to bring electricity to 20 million people in und...
02-25 Henry Hub Average Natural Gas Spot Prices

02/25 Henry Hub Average Natural Gas Spot Prices

The Henry Hub is the pricing point for natural gas futures contracts traded on the New York M...
 GDF Suez wants Areva to deliver nuclear reactors, wind turbines

GDF Suez wants Areva to deliver nuclear reactors, wind turbines

GDF Suez says it received guarantees from Areva for planned nuclear reactors in Turkey and wi...
 CB&I: We’re not liable for $247mn nuclear power project penalties

CB&I: We’re not liable for $247mn nuclear power project penalties

Chicago Bridge & Iron (CB&I, NYSE: CBI) say they should not be liable for any of the ...

Power Engineering Current Issue

03/01/2014
Volume 118, Issue 3
1403PE-cover

Products Showcase

Dynamic Fluoride Ion cleaning DFIC of industrial natural gas turbines Hi-Tech Furnace Systems

Dynamic Fluoride Ion Cleaning of IGT Parts

The Dynamic Fluoride Ion Cleaning (DFIC) Process from Hi-Tech Furnace Systems is able to clean deep, narrow cracks of oxides by cycling between negative, atmospheric, and positive pressure.

Archived Articles

2000 | 2001 | 2002 | 2003 | 2004 | 2005 | 2006 | 2007 | 2008 | 2009 | 2010 | 2011 | 2012 | 2013

Buyers Guide Product Listings

Pipeline Repair and Rehabilitation

Tyfo® Fibrwrap® Pipe Rehabilitation System is a...

RETROFIT

Braden's retrofit strengths are divided into tw...

Power Industry Wire News

Aricent Expands IoT Commitment, Creates Dedicated IoT Engineering Portfolio

Aricent Expands IoT Commitment, Creates Dedicated IoT Engineering Portfolio

Intergraph(R) CADWorx & Analysis University Express in India During March to Include Sessions on Designing Plants and Offshore Facilities

Intergraph(R) CADWorx & Analysis University Express in India During March to Include Se...

What's Coming to the Energy Sector in 2015?

What's Coming to the Energy Sector in 2015?

SL Series Is Tinius Olsen's New Generation of Hydraulic Universal Testing Machines

SL Series Is Tinius Olsen's New Generation of Hydraulic Universal Testing Machines

Manitok Energy Inc.'s CEO Mass Geremia Interviewed by The Energy Report

Manitok Energy Inc.'s CEO Mass Geremia Interviewed by The Energy Report

Power Engineering

Article Archives for Power Engineering Magazine

Continuing Education

Professional Development Hours

To access a course listing associated to a specific topic listed below, click on the topic of choice from the list below.

Latest Energy Jobs

View more Job Listings >>