GLASGOW, Scotland, Aug. 24, 2001 — ScottishPower, an international utility, today announced that its US subsidiary PacifiCorp filed on August 23, 2001 with the Utah Public Service Commission (PSC) to recover $104 million related to purchased power and other impacts arising from losing Hunter unit 1 from PacifiCorp's generation portfolio.

On February 9, 2001, the Utah PSC authorized PacifiCorp to defer costs related to the Hunter outage. The 430 MW unit was returned to service in early May 2001.

In Oregon & Wyoming, proceedings are already underway to account for and recover excess net power costs incurred as a result of market conditions and the Hunter unit outage. A filing to recover deferred costs in Idaho is scheduled to be made by December 2001.

The ScottishPower (NYSE: SPI - news) group supplies energy to millions of business and domestic customers across the UK, where it serves approximately one in five British households, and in the Western United States, through its merger with PacifiCorp in November 1999. The group is also active in telecommunications and retains a majority interest of its telecom subsidiary Thus (LSE: THUS).

ScottishPower's ADR, equivalent to four ordinary shares, trades on the New York Stock Exchange under the symbol SPI. ScottishPower's ordinary shares trade on the London Stock Exchange. Prices may be accessed on Bloomberg under the symbols SPI and SPW LN, on the Reuter Equities 2000 Service under SPI.N and SPW.L and on Quotron under SPWU.EU.

Sponsored by FLSmidth
Font Sizes:
Recommend this article Recommend this article () You recommended this article You recommended this article ()
Follow Power Engineering on Twitter

Latest News

Shutterstock coal production trucks

Weekly Coal Production

The Weekly Coal Production shows how much coal is being produced across the U.S.

Federal Reserve Bank of Dallas Weekly Economic Indicators financial business

The Federal Reserve Bank of Dallas' Economic Indicators

The Federal Reserve Bank of Dallas offers a glimpse into how the markets are doing domestical...

Kvaerner awarded contract for gas-fired power plant in Delaware

Kvaerner North American Construction Inc. and its joint venture partner, Parsons Brinckerhoff...

Canadian Solar purchases two solar projects

Canadian Solar Inc. has acquired a majority interest in two utility-scale solar power project...

Operators Restart Unit 2 at PPL Susquehanna

Unit 2 at the PPL Susquehanna nuclear power plant near Berwick, Pa. resumed generating electr...

Settlement agreement limits cost recovery at Edwardsport

The Indiana Utility Regulatory Commission (IURC) on Dec. 27 modified and approved a settlemen...

Toshiba in talks to sell portion of Westinghouse nuclear unit

Toshiba Corp is in talks  to sell up to 16% of its stake in the Westinghouse Electric Co...

Utah nixes nuclear waste storage facility

Plans to park radioactive waste at a storage facility in Utah have been officially called off.

Current Magazine Issue

05/01/2013
Volume 117, Issue 5
1305pe-cover

Watch POWER-GEN 2012

Power Engineering

Article Archives for Power Engineering Magazine

Archived Articles

2000 | 2001 | 2002 | 2003 | 2004 | 2005 | 2006 | 2007 | 2008 | 2009 | 2010 | 2011 | 2012 | 2013

Continuing Education

Professional Development Hours

To access a course listing associated to a specific topic listed below, click on the topic of choice from the list below.