AES fined $17 million for pollution from power plant

Dec. 14, 2000—AES Corp. will pay a $17 million fine for surpassing air emissions limits at its Alamitos power plant facility but will be allowed to operate the plant without penalties during California electric power emergencies.

Under an agreement with California air regulators, AES can operate the plant while it pursues permits to install pollution control devices mandated by the environmental authorities. With California Independent System Operator desperate for megawatts to keep the lights on, officials moved quickly to reach a settlement to get the plant back in service.

AES said the plant was up and running as soon as an agreement was reached with environmental officials.

The South Coast Air Quality Management District and AES Thursday reported reaching a settlement of air pollution allegations at the plant resulting in the fine and the agreement to install selective catalytic reduction devices on four units at Alamitos. The emissions violations allegedly occurred during the third and fourth quarter of 2000. The violations, fines, and an abatement order were levied against AES in mid-November.

The 2,083 MW gas-fired generating plant was shut down after the company received the Nov. 16 abatement order, says Aaron Thomas, spokesman for AES Pacific, a unit of AES.

The settlement removes uncertainty relating to threatened court action by the management district regarding allegations AES exceeded its allowed emissions. It also allows the plant to operate during any ISO declared Stage 1,2, or 3 emergency without penalties, says Sam Atwood, spokesman for South Coast Air Quality.

The settlement also requires AES to file for permits within 15 days for the installation of the selective catalytic reduction devices. The permitting process could take as long as 6 months, says Atwood.

�We are committed to do it as quickly as possible, but we can�t control the public comment period that could delay the permits,� he says.

Sponsored by FLSmidth

Related Articles

Indiana Michigan nears permit for Rockport Unit 1 SCR project

The Indiana Office of Air Quality (OAQ) is taking comment until Jan. 31 on a draft air permit revision allowing the Indiana Michigan Power unit of American Electric Power (NYSE: AEP) to install a new air emissions control on one of the two, 1,300-MW units at the coal-fired Rockport plant.

New Mexico San Juan Generating Station coal-fired shut down pollution Public Regulation Commission

New Mexico regulators weigh power plant proposal

State regulators are taking testimony on a plan that calls for shutting down part of an aging coal-fired power plant in northwestern New Mexico that provides electricity to more than 2 million people in the Southwest.

Follow Power Engineering on Twitter
Latest News

FERC approves NextEra & Hawaiian Electric merger

The Federal Energy Regulatory Commission (FERC) approved a proposed merger between NextEra En...

NRC won’t investigate SCE in SONGS shut down

The U.S. Nuclear Regulatory Commission (NRC) said it is dropping its investigation of Souther...

Prairie Island nuclear Unit 2 back online after false fire alarm

Prairie Island 2 nuclear power plant in Minnesota is back online three weeks after a false fi...

Gov. Nixon, EaglePicher Technologies holds groundbreaking ceremony for new Li-ion battery center

Missouri Gov. Jay Nixon joined officials with EaglePicher Technologies for a groundbreaking c...

NuScale completes upper module mockup of small nuclear reactor

NuScale Power LLC said it completed fabrication and assembly of a full-scale, upper module mo...

Farley nuclear power plant goes offline for scheduled outage

Workers at the Farley nuclear power plant in Alabama took Unit 1 offline for a scheduled refu...

GE Hitachi Nuclear Energy dedicates reactor training area

GE Hitachi Nuclear Energy (GEH) dedicated its new boiling water reactor under-vessel training...

Shell Chemical nears air permit for 250-MW power project in Pennsylvania

Shell Chemical Appalachia LLC is close to an air permit from the Pennsylvania Department of E...

Power Engineering Current Issue

12/01/2014
Volume 118, Issue 12
1412pe-cover1
Products Showcase
Dynamic Fluoride Ion cleaning DFIC of industrial natural gas turbines Hi-Tech Furnace Systems

Dynamic Fluoride Ion Cleaning of IGT Parts

The Dynamic Fluoride Ion Cleaning (DFIC) Process from Hi-Tech Furnace Systems is able to clean deep, narrow cracks of oxides by cycling between negative, atmospheric, and positive pressure.

Archived Articles

2000 | 2001 | 2002 | 2003 | 2004 | 2005 | 2006 | 2007 | 2008 | 2009 | 2010 | 2011 | 2012 | 2013

Power Industry Wire News

Perma-Fix Reports Results for Year Ended December 31, 2014 Including 33% Increase in Revenue, 120% Increase in Gross Profit, $2.2 Million of Adjusted EBITDA and $796,000 of Net Income for the Fourth Quarter of 2014

Perma-Fix Reports Results for Year Ended December 31, 2014 Including 33% Increase in Re...

Rhombus Energy Solutions, Inc. Acquires Energy Development Associates, LLC

Rhombus Energy Solutions, Inc. Acquires Energy Development Associates, LLC

Sharp Electronics' SmartStorage(R) Behind-the-Meter Energy Storage Solution Installed on Baker Electric Facility in Southern California

Sharp Electronics' SmartStorage(R) Behind-the-Meter Energy Storage Solution Installed o...

Torchlight Energy Begins Drilling First Well in Its Orogrande Project

Torchlight Energy Begins Drilling First Well in Its Orogrande Project

ZBB Agile Flow Battery Receives Key Third Party Performance Validation

ZBB Agile Flow Battery Receives Key Third Party Performance Validation

Power Engineering

Article Archives for Power Engineering Magazine

Continuing Education

Professional Development Hours

To access a course listing associated to a specific topic listed below, click on the topic of choice from the list below.

Latest Energy Jobs

View more Job Listings >>