AES fined $17 million for pollution from power plant

Dec. 14, 2000—AES Corp. will pay a $17 million fine for surpassing air emissions limits at its Alamitos power plant facility but will be allowed to operate the plant without penalties during California electric power emergencies.

Under an agreement with California air regulators, AES can operate the plant while it pursues permits to install pollution control devices mandated by the environmental authorities. With California Independent System Operator desperate for megawatts to keep the lights on, officials moved quickly to reach a settlement to get the plant back in service.

AES said the plant was up and running as soon as an agreement was reached with environmental officials.

The South Coast Air Quality Management District and AES Thursday reported reaching a settlement of air pollution allegations at the plant resulting in the fine and the agreement to install selective catalytic reduction devices on four units at Alamitos. The emissions violations allegedly occurred during the third and fourth quarter of 2000. The violations, fines, and an abatement order were levied against AES in mid-November.

The 2,083 MW gas-fired generating plant was shut down after the company received the Nov. 16 abatement order, says Aaron Thomas, spokesman for AES Pacific, a unit of AES.

The settlement removes uncertainty relating to threatened court action by the management district regarding allegations AES exceeded its allowed emissions. It also allows the plant to operate during any ISO declared Stage 1,2, or 3 emergency without penalties, says Sam Atwood, spokesman for South Coast Air Quality.

The settlement also requires AES to file for permits within 15 days for the installation of the selective catalytic reduction devices. The permitting process could take as long as 6 months, says Atwood.

�We are committed to do it as quickly as possible, but we can�t control the public comment period that could delay the permits,� he says.

Sponsored by FLSmidth

Related Articles

EPA unveils SO2 scrubber-reliant haze plan for Texas

The U.S. Environmental Protection Agency is proposing new regional haze SO2 reduction requirements for Texas based on a series of presumed scrubber installations and scrubber upgrades on 14 coal-fired power plant units.

National Grid joins proposal for 300-mile cable in Maine

Utility giant National Grid is partnering with a company that specializes in underwater cable projects in an alliance seeking to build a 300-mile cable to bring Canadian hydropower and Maine wind power to Greater Boston to help meet the energy needs of power-hungry southern New England, the companies announced Tuesday.

Follow Power Engineering on Twitter

Latest News

NCC Report: DOE must develop stronger policy to foster adequate carbon capture and storage

The National Coal Council (NCC) today released a new study in response to a request by Secret...
CASL DOE light water reactors LWR research and development

DOE extends funding for light water reactor research consortium

MHPS to take over thermal power business

Effective April 1, Mitsubishi Hitachi Power Systems (MHPS) will take over the business in the...

Builder projects 18-month delay for nuclear plant in Georgia

Southern Co. (NYSE: SO) said the firms building its new nuclear power plant in Georgia estima...

Alstom to maintain Olkiluoto nuclear island equipment

Alstom was awarded a five-year contract to maintain equipment at the Olkiluoto nuclear power ...
2014 Projects of the Year

Power Engineering Photo of the Day

Capstone Turbine corporation shale oil and gas microturbines Horizon Power Systems

Capstone Turbine Receives Follow-On Order for Fifteen C65s from Horizon Power Systems

Capstone Turbine Corp. received an order for 15 C65 microturbines for shale oil and gas custo...
Yucca Mountain Nevada nuclear spent fuel waste repository DOE application NRC review SER evaluation volumes

NRC publishes last two volumes of Yucca Mountain safety evaluation

The NRC published two more volumes of its safety evaluation on a geologic high-level nuclear ...

Power Engineering Current Issue

03/01/2014
Volume 118, Issue 3
1403PE-cover

Products Showcase

Dynamic Fluoride Ion cleaning DFIC of industrial natural gas turbines Hi-Tech Furnace Systems

Dynamic Fluoride Ion Cleaning of IGT Parts

The Dynamic Fluoride Ion Cleaning (DFIC) Process from Hi-Tech Furnace Systems is able to clean deep, narrow cracks of oxides by cycling between negative, atmospheric, and positive pressure.

Archived Articles

2000 | 2001 | 2002 | 2003 | 2004 | 2005 | 2006 | 2007 | 2008 | 2009 | 2010 | 2011 | 2012 | 2013

Power Industry Wire News

Intergraph(R) Releases PV Elite(R) 2015 With New Modeling Capabilities and Other Productivity Enhancements

Intergraph(R) Releases PV Elite(R) 2015 With New Modeling Capabilities and Other Produc...

Utility Execs Explain How to Centralize Crew Management Before and After Storms

Utility Execs Explain How to Centralize Crew Management Before and After Storms

Con Edison 2016 Rate Plan Cites Reliability, Storm Prep, Better Technology

Con Edison 2016 Rate Plan Cites Reliability, Storm Prep, Better Technology

Diesel Particulate Matter (DPM) Testing Evidences 20% Reduction With Use of CyberFuels Dynamo(TM) Cetane Booster

Diesel Particulate Matter (DPM) Testing Evidences 20% Reduction With Use of CyberFuels ...

Miller Energy Declares Cash Dividends on Its Series B, Series C and Series D Preferred Stock

Miller Energy Declares Cash Dividends on Its Series B, Series C and Series D Preferred ...

Power Engineering

Article Archives for Power Engineering Magazine

Continuing Education

Professional Development Hours

To access a course listing associated to a specific topic listed below, click on the topic of choice from the list below.

Latest Energy Jobs

View more Job Listings >>